This is the number nobody volunteers at the showroom, and it is the one that decides whether you cook Thanksgiving in your own kitchen.
Showroom cabinet lead times in 2026 run about 3 to 8 weeks for semi-custom and 6 to 16 weeks for fully custom, and that clock starts at final order, not at your first appointment — design revisions happen before it starts, so a “six-week” kitchen is often nine weeks from the day you walked in. Order in the March-to-June rush and add another week or two.
The gap between the quoted lead time and the real one
Showrooms quote the lead time from the day the order is finalized. You experience it from the day you walked in. Between those two dates sits the design phase — measurements, revisions, the drawing you did not love, the door sample that had to be reordered — and that phase routinely eats two to four weeks before the factory clock even starts.
So when someone says six weeks, plan on nine. When someone says twelve, plan on fifteen. And if you are ordering between March and June, when the whole industry is at peak capacity, add another one to two weeks on top.
Lead times by cabinet type, 2026
- RTA and stock cabinets — 1 to 2 weeks. Ready-to-assemble, limited sizes and finishes. Fast and cheap, and it shows.
- Semi-custom — 3 to 8 weeks, averaging about six. This is what most Long Island kitchens actually are. Standard boxes, wide choice of doors, finishes and modifications.
- Fully custom — 6 to 16 weeks or longer. Built to your dimensions. Worth it for an awkward room, expensive and slow for a rectangular one.
- Already in a warehouse — days. Rare, because it only happens when somebody else's order got cancelled.
What the wait actually costs you
It is not just inconvenience. A long lead time compounds into real money and real risk.
- You live without a kitchen longer. Six weeks of takeout for a family of four is not a rounding error.
- The permit clock can run. A Brookhaven building permit is valid one year from issue, and a stalled cabinet order is one of the more common reasons a job drifts. More on the Brookhaven clock.
- Price protection may lapse. Ask specifically how long your quoted price is held. Some hold to delivery, some to a fixed date.
- Your contractor's schedule moves on. A crew booked for March does not sit idle waiting for June cabinets. You go back in the queue.
The in-stock alternative
There is one honest way to skip the wait entirely: buy cabinets that already exist. That is what we sell.
Our installed kitchens run $20,000 to $30,000 — cabinets, quartz counters, an island, a new sink and the plumbing, demo and haul-away, and labor. Not included: backsplash, appliances, flooring, and handles on most sets. The price works for a specific and finite reason: the cabinet sets came from projects that were cancelled after the cabinets had already been ordered, so they are paid for and sitting in our warehouse. When they are gone the price goes back to market.
The sets are physically in our warehouse in East Patchogue. There is no factory, no lead time, and no order to be delayed — you can come look at them. The sets currently available are here.
The honest limitation: you are choosing from what exists rather than specifying what you want. If you have your heart set on a particular door in a particular color, wait for the factory. If you want a good kitchen soon at a price below the market, this is faster and cheaper than anything a showroom can offer.
Questions to ask before you sign
- When does the lead-time clock start — today, or at final order approval?
- Is that lead time to the warehouse, or to my house?
- How long is my price held?
- What happens to the schedule if the delivery slips two weeks?
- Is anything in this order on backorder right now?
Get the answers in writing. The rest of what belongs in a kitchen quote is here.
Want a real number on your kitchen?
We measure on site and price it in writing. Free, no obligation, no showroom.
Towns we do kitchens in
We are based in East Patchogue and most of our kitchen work is in Brookhaven and Islip, but we go where the job is. If you are inside an incorporated village, the village building department governs rather than the town.
- Brookhaven — Patchogue, East Patchogue, Medford, Holbrook, Farmingville, Coram, Selden, Bellport, Shirley, Mastic, Centereach
- Islip — Islip, Bay Shore, West Islip, East Islip, Sayville, Bohemia, Oakdale, Brentwood
- Smithtown — Smithtown, Nesconset, Commack, Kings Park, St James, Hauppauge
- Huntington — Huntington, Northport, Dix Hills, Melville, Greenlawn, Huntington Station
- Babylon — Babylon, West Babylon, North Babylon, Lindenhurst, Copiague, Deer Park
- Brookhaven villages — Port Jefferson, Patchogue village, Bellport and Lake Grove run their own building departments
If your town is not on the list, call anyway — the list is where we work most, not a boundary. Anything from Nassau through the Twin Forks is fair game; we tell you honestly if travel makes a small job uneconomical.
Frequently Asked Questions
How long do kitchen cabinets take to arrive?
In 2026, stock and RTA cabinets arrive in one to two weeks, semi-custom in three to eight weeks, and fully custom in six to sixteen weeks or longer. The lead time starts at final order approval, not at your first design appointment.
Why is my kitchen taking longer than the six weeks I was quoted?
The quoted lead time usually starts when the order is finalized, and the design phase before that commonly adds two to four weeks. Orders placed during the March to June peak season can take an extra one to two weeks as well.
Can I get kitchen cabinets faster on Long Island?
Yes, if you buy cabinets that already exist rather than ordering from a factory. We hold complete sets in our warehouse in East Patchogue that came from cancelled projects, so there is no manufacturing lead time at all.
Does the season affect cabinet lead times?
Yes. March through June is the busiest period for kitchen remodels and manufacturers and freight carriers run at peak capacity. The same order placed in January often arrives faster than one placed in April.
Related Reading
- The cheapest honest way to redo a kitchen — when in-stock wins
- Kitchen remodel timeline — the whole schedule, not just cabinets
- Kitchen remodel cost — 2026 Long Island numbers
- Refacing vs replacing — the fast, cheap alternative
- Kitchen permits by town — what filing adds to the schedule